With various run-ups in heating oil over the years, we looked into getting natural gas, but running a line to our house wasn't financially viable. A few years ago, three houses on our left (original two bedroom capes) became "knockdown" McMansion spec houses, and gas service was now available to us (not that anyone asked!).
A few winters ago was really miserable - much colder than usual, and I (we ?) decided it made sense to get a gas fireplace for the first floor, which we (I ?) hoped would enable enjoying the space (den, TV room, dinners, etc), and maybe even entertaining more during the cold season.
This coincided with repeated occurrences of flooding in the back of the house, primarily the den extension - resulting from the the backyard sloping toward the house, and repeated failed attempts at drainage. The drainage system(s) would work OK most of the time, but then a torrential storm came, and we'd have another ruined carpet, or laminate floor in the den. Multiple attempts to shop vacuum water out of the carpeting, then shampoo machine, didn't help. Tearing up the water-logged carpeting from the last flooding, we decided the next flooring in the den would be tile - much easier to deal with, in the likely event of future flooding.
In addition to the flooding problem, the north facing kitchen extension roof was very low pitched, and recurring ice dams resulted in replacing the entire roof system (~1992) including joists - yet ice dams continued to be a problem, with resulting roofing rot, and leaks, and significant water damage/mold in one corner of the kitchen.
Overall scope of the project:
- dealing with the (massive) roof leaks.
- install new floor
- install gas service line from gas meter (side of the house) to the location of the fireplace (particularly challenging due to concrete slab).
- construction of fireplace platform, venting, electrical, drywall, wallpaper, etc etc etc.
- two mantel surrounds (see through fireplace, as shown in the pic) and hearth.
Pic taken after Thanksgiving 2014: demolition, installation of new header, rough framing for
fireplace venting and platform, and electrical.
Pending items:
- Building permit.
- Fabricate & install mantel(s) and surround(s) - 'see-through fireplace', so two of these
are needed, and I'm doing different design on each side ... just to make it more interesting :-) - Set up the fireplace itself, including converting the propane unit purchased to natural gas, install ceramics log set, remote control, and auxiliary fan. I'll probably hire a professional fireplace guy for this - tho' I'm confident I could do it myself ... would just take me muuuuuchhh longer!
Along the way I lined up estimates for the roof and flooring - yet decided to do the work myself. I'm reasonably certain these decisions were not always in the best interest of marital harmony - yet the outcome of virtually all the work I've done has been, as I call it, a "pro job" (though these days, that doesn't always mean that much...)
.
I'll follow and post pics of the sub-projects
Den Floor - winter 2015 (some pics previously posted)
18 inch porcelain tiles were installed with 'medium set' mortar ( *crazy* hard to mix ),
an effective solution for the sloping floor (about an inch difference in height) - this type
of mortar can be installed up to an inch thick.
Removed ~200 square feet of existing mastic (black-tar-adhesive ... essentially sticky
kryptonite!) from the concrete floor using a 7-inch disc grinder and specialized diamond
-encrusted tool 'Diamabrush' and DIY dust shroud made from a two gallon plastic bucket
and PVC shower drain.
Roof - summer 2015
- Removed existing roof, had *four* layers of shingles (building code permits up to three!)
- Installed fireplace venting (vertical vent, through the roof).
- Reworked valley, installed ice/water shield membrane ...had to do this twice :-(
- 45x45 skylight had to be removed, disassembled, damaged copper flashing repaired
(nail holes where they weren't supposed to be) and reinstalled. *Crazy* heavy to move
by myself.
- Drywall, paint, wallpaper
- Electrical
Building Permit Applications - Spring 2016
- Drawings by yours-truly, and stamped by PE (thanks again, Ryan!)
- Plumbing permit (completed), construction permit (pending)
Pic of one of the permit application drawings (can you tell I took three years of drafting classes in Jr./Sr. High School ?):
Yeah! You can do it! I love the title of this post... it truly captures the epic nature of the project.
ReplyDelete